Structural Crack Repair & ComplianceNorthbridge, NSW

Fire stair wall repair across four levels with full NSW Building Commissioner compliance achieved in five days

The Challenge: A reinforced concrete fire stair wall across four levels of an occupied residential building in Northbridge was displaying structural defects: visible cracking, localised wall movement and bowing, and concrete spalling with delamination. The NSW Building Commissioner's office had issued a formal rectification order.
Our Solution: TRD Remedial was engaged to develop and deliver the repair methodology across all four levels. The full repair program was executed in five days and included epoxy crack injection, concrete spalling repairs, reprofiling and rendering, and concrete cutting with localised demolition and reinstatement.
Results: The full repair scope was completed within five days. Structural cracking was stabilised, all affected wall sections reinstated, and the building returned to compliance. The rectification order issued by the NSW Building Commissioner's office was formally closed.

This Structural Crack Repair & Compliance project by TRD Remedial in Northbridge, NSW demonstrates our expertise in delivering professional building remediation solutions across Sydney and Greater NSW. Completed within 5 Days.

Structural Wall Repairs & Building Commissioner Compliance — Northbridge
2025Structural Crack Repair & ComplianceNorthbridge, NSW5 Days

Structural Wall Repairs & Building Commissioner Compliance — Northbridge

Fire stair wall repair across four levels with full NSW Building Commissioner compliance achieved in five days

Back to Projects

The Challenge

A reinforced concrete fire stair wall across four levels of an occupied residential building in Northbridge was displaying structural defects: visible cracking, localised wall movement and bowing, and concrete spalling with delamination. The NSW Building Commissioner's office had issued a formal rectification order.

Our Solution

TRD Remedial was engaged to develop and deliver the repair methodology across all four levels. The full repair program was executed in five days and included epoxy crack injection, concrete spalling repairs, reprofiling and rendering, and concrete cutting with localised demolition and reinstatement.

Results

The full repair scope was completed within five days. Structural cracking was stabilised, all affected wall sections reinstated, and the building returned to compliance. The rectification order issued by the NSW Building Commissioner's office was formally closed.

4

Levels Repaired

5

Days to Complete

Closed

Commissioner Order